At ARDOT Tract 23X in Greenwood, Meyers Construction was contracted to remove a manufactured home and carport, remove the septic system, close water and gas services, and treat disturbed ground with hay and seed.

Open ground and surrounding context at Tract 23X in a later project view.
LATER CONDITIONOpen ground and surrounding context at Tract 23X in a later project view.

Project at a Glance

Project at a Glance

Location: 1114 Excelsior Road, Greenwood, Arkansas. Client: ARDOT. Project reference: 040862 Tract 23X. Bid-basis improvements: approximately 1,224 SF manufactured home and 500 SF carport. Other scope: septic removal, water/gas closure, hay-and-seed treatment.

Verified contract scope

Meyers Scope of Work

The executed work list names manufactured-home and carport removal, septic-system removal, water and gas cut-and-cap, and hay-and-seed treatment of disturbed areas. Debris disposal is covered by the demolition contract conditions.

Execution

Execution / Field Approach

The removal limits include a structure, carport, septic system, and utility services, followed by disturbed-ground treatment.

Project media

What the project photos show

Documented result

Later site condition

The later images show open ground, grass/straw, and retained trees.